A Gantt chart is a visual planning tool that shows project activities across a timeline.
A Gantt chart helps teams understand what needs to happen, when activities are planned and who is responsible for progressing them.
Activities are listed vertically, with time shown horizontally. Coloured bars indicate when each activity is expected to start, how long it may take and when it should be completed.
A Gantt chart can also show:
A Gantt chart provides an overview of the project schedule, while an action plan usually contains more detail about the individual actions, owners, deadlines and progress updates. Gantt chart is a visual timeline of tasks that helps a team/individual identify what tasks should be done and by when.
Improvement projects often involve several activities happening across different timescales. A Gantt chart makes the overall project schedule visible, helping teams coordinate work and understand how different activities fit together.
A Gantt chart can help you:
The value of a Gantt chart comes from making the project timeline easier to understand, discuss and update. It should support planning and communication rather than become an administrative task.
1. Clarify the project aim and scope
Start by reviewing the project charter, improvement aim and agreed scope. This helps ensure that the activities included in the Gantt chart remain focused on what the project is trying to achieve.
2. Identify the main activities
Review the action plan and identify the activities needed to progress the project. These will vary depending on the project.
Start with the main areas of work rather than adding every small task. More detailed actions can remain within the action plan.
3. Identify milestones
Add important milestones that indicate progress or key decision points.
Milestones are usually shown as points in time rather than activities with a duration.
4. Agree the timeline
Decide which timescale is most useful for the project, such as:
Use a level of detail that is appropriate to the length and complexity of the work. A short project may need a weekly timeline, while a longer programme may be easier to manage using months or quarters.
5. Estimate activity duration
For each activity, estimate:
Use this information to add a bar across the relevant part of the timeline.
Timescales are estimates and may need to change as the team learns more about the system and tests different approaches.
6. Identify owners
Assign a named owner to each activity. The owner does not need to complete all the work alone but is responsible for ensuring that the activity progresses and is updated.
7. Identify dependencies
Consider whether any activities depend on others being completed first.
For example:
Showing dependencies helps teams understand how delays in one area could affect the wider project.
8. Agree how progress will be shown
Use clear and consistent status categories, such as:
Colours can make the chart easier to interpret but include text labels or another indicator so that meaning does not depend on colour alone.
Agree on the definitions of each status so they are used consistently. The current page’s emphasis on agreeing operational definitions for status remains useful here.
9. Review and update the chart
Review the Gantt chart regularly during project meetings.
Use the review to:
Changes to the timeline do not necessarily mean the project has failed. Improvement work often requires teams to adapt their plans as learning emerges.